ROBG 332

ROBG-332 “Joint Volunteering for a Safer Life”

What’s the goal?

The project’s objective is to improve the theoretical and practical preparedness of volunteer emergency response units and enhance the coordination and efficient reaction in case of disaster in the cross-border area.

What’s the budget?

998,815.75 euro, out of which 848,993.36 euro ERDF

Target at the half of the implementation period: 30,057 euro for LB, 14,871 euro for B2, 5,000 euro for B3, 3,880 euro for B4

Who is doing it?

Lead Beneficiary (LB): Municipality of Tutrakan

Beneficiary 2 (B2): Directorate General Fire Safety and Civil Protection – Ministry of the Interior (BG)

Beneficiary 3 (B3): General Inspectorate for Emergency Situations - Ministry of Internal Affairs (RO)

Beneficiary 4 (B4): National Association of Volunteers in the Republic of Bulgaria

When is it happening?

Start date: 12.09.2018

End date: 11.09.2021

Duration: 36 months

Where is it happening?

Pleven, Veliko Tarnovo and Silistra in Bulgaria

Dolj and Constanta in Romania

How is it going to happen?

  • Risk analysis of the cross border area
  • Procurement of complete protective suits for firefighting and training tower
  • Development of a volunteer emergency response plan for common actions
  • Development of a joint training program for volunteer emergency response units
  • Conduct theoretical and practical trainings in Bulgaria and Romania

What will be the results (what’s the contribution to the Programme)?

Programme outputs:4,779,754 people benefiting from actions of risk management, 4591666 people benefiting from flood protection measures, 4,779,754 people benefiting from forest fire protection measures, 5 joint partnerships in the field of joint early warning and emergency response

Programme results: increased quality of the joint risk management in the CBC area from inappropriate (2.00) to satisfactory (3.00)

Project status

The project passed its first six months of implementation. Project management teams were set up, promotional materials were contracted for delivery, press conference was organized and a press release was published in newspapers. Tender dossier was elaborated for the risk analysis of the cross-border area, the work on the procurement of specialized equipment started and the contract for development of procurement files for the works and supervision of the Training center was signed.

Pictures

September 2019
Mo Tu We Th Fr Sa Su
26 27 28 29 30 31 1
2 3 4 5 6 7 8
9 10 11 12 13 14 15
16 17 18 19 20 21 22
23 24 25 26 27 28 29
30 1 2 3 4 5 6

The content of this website does not necessarily represent the official position of the European Union. The initiators of the site are the sole responsible for the information provided through the site.