DJ-MN: BET-CON (ROBG-375)
Dolj – Montana: Joint steps for a better connectivity
What’s the goal?
The overall objective of the project is to improve the development and coordination of cross-border transport systems for better connections to TEN-T network from Dolj and Montana counties. |
What’s the budget?
7,689,268.62 euro, out of which 6,535,878.32 euro ERDF
Who is doing it?
Lead Beneficiary (LB): Territorial Administrative Unit - Dolj County (Romania)
Beneficiary 2 (B2): Road Infrastructure Agency (Bulgaria)
When is it happening?
Start date: 11.07.2018
End date: 10.07.2021
Duration: 36 months
Where is it happening?
Dolj in Romania
Montana in Bulgaria
How is it going to happen?
|
What will be the results (what’s the contribution to the Programme)?
Programme outputs:19.84 km of upgraded road, 3 joint mechanisms to facilitate the connection of tertiary nodes to TEN-T infrastructure
Programme results: 13,546 people served by modernized infrastructure leading to TEN-T
Project status
The project is currently under implementation, having the wollowing results:
LB completed the procedure for awarding the works contract for upgrading the County Road DJ 561, initiated in the electronic public procurement system. The contract will be signed after the end of the appeal period (07.09.2020).
B2 signed the contract on 10.12.2019 for upgrading of Road II-81 and the contract for the works supervision on 18.06.2020. On 17.07.2020, Protocol 2 for opening the construction site was signed, starting the construction works.
In terms of project promotion, on 26.07.2018 LB organized the launching press conference of the project in Craiova, event attended by 21 participants.