ROBG 375

DJ-MN: BET-CON (ROBG-375)

Dolj – Montana: Joint steps for a better connectivity

What’s the goal?

The overall objective of the project is to improve the development and coordination of cross-border transport systems for better connections to TEN-T network from Dolj and Montana counties.

What’s the budget?

7,689,268.62 euro, out of which 6,535,878.32 euro ERDF

Who is doing it?

Lead Beneficiary (LB): Territorial Administrative Unit - Dolj County (Romania)

Beneficiary 2 (B2): Road Infrastructure Agency (Bulgaria)

When is it happening?

Start date: 11.07.2018

End date: 10.12.2022

Duration: 53 months

Where is it happening?

Dolj in Romania

Montana in Bulgaria

How is it going to happen?                      

  • A road map of Dolj and Montana highlighting the black spots on the roads
  • Awareness campaign for speed managing and human tolerance on roads
  • Technical Design and technical assistance from the designer
  • Upgrading works for a section of the road DJ 561 B
  • Upgrading works for a section of the Road II-81 Kostinbrod-Berkovitsa-Montana
  • Works Supervision services for both LB and B2
  • A common traffic safety system consisting of 8 solar radar speed signs Public events

What will be the results (what’s the contribution to the Programme)?

Programme outputs: 19.84 km of upgraded road, 3 joint mechanisms to facilitate the connection of tertiary nodes to TEN-T infrastructure

Programme results: 13,546 people served by modernized infrastructure leading to TEN-T

Project status

The Project is in the 38th month of implementation out of the 53 months.

Lead Beneficiary:

LB execution of the construction works on 17.12.2020 at the request of the constructor, which identified the need for revision of the Technical Project because of some problems regarding the topographic study. The Revised Technical Project was received by LB on 05.07.2021. On 26.07.2021 the technical visa for the revised topographic study was obtained from the Cadastre Office. The building permit for the Revised Technical Project was obtained by LB on 19.08.2021, so the construction works on behalf of LB are expected to be restarted.

Beneficiary 2:

On behalf of B2, the construction works started on 17.07.2020 when the site opening protocol was signed. The main construction works for the investment objective “Upgrading of Road II-81”, have been completed. The activities related to the acceptance of the completed works have started.