DJ-MN: BET-CON (ROBG-375)
Dolj – Montana: Joint steps for a better connectivity
What’s the goal?
The overall objective of the project is to improve the development and coordination of cross-border transport systems for better connections to TEN-T network from Dolj and Montana counties. |
What’s the budget?
7,689,268.62 euro, out of which 6,535,878.32 euro ERDF
Who is doing it?
Lead Beneficiary (LB): Territorial Administrative Unit - Dolj County (Romania)
Beneficiary 2 (B2): Road Infrastructure Agency (Bulgaria)
When is it happening?
Start date: 11.07.2018
End date: 03.10.2023
Duration: 62 months and 23 days
Where is it happening?
Dolj in Romania
Montana in Bulgaria
How is it going to happen?
|
What will be the results (what’s the contribution to the Programme)?
Programme outputs: 19.84 km of upgraded road, 3 joint mechanisms to facilitate the connection of tertiary nodes to TEN-T infrastructure
Programme results: 13,546 people served by modernized infrastructure leading to TEN-T
Project status
The project is in the implementation period. The following results were achieved:
Lead Beneficiary:
LB started the execution of the construction works. As af August, a 93% progress was registered.
Beneficiary 2:
The construction works for the investment objective “Upgrading of Road II-81 from km 86+289 to km 94+000 ”, have been completed. On the upgraded road sector, being part of B2 investment, were installed 4 solar radar speed signs. The road use authorization was issued on 01.02.2022.