DJ-MN: BET-CON (ROBG-375)
Dolj – Montana: Joint steps for a better connectivity
What’s the goal?
The overall objective of the project is to improve the development and coordination of cross-border transport systems for better connections to TEN-T network from Dolj and Montana counties. |
What’s the budget?
7,689,268.62 euro, out of which 6,535,878.32 euro ERDF
Who is doing it?
Lead Beneficiary (LB): Territorial Administrative Unit - Dolj County (Romania)
Beneficiary 2 (B2): Road Infrastructure Agency (Bulgaria)
When is it happening?
Start date: 11.07.2018
End date: 16.07.2023
Duration: 60 months and 6 days
Where is it happening?
Dolj in Romania
Montana in Bulgaria
How is it going to happen?
|
What will be the results (what’s the contribution to the Programme)?
Programme outputs: 19.84 km of upgraded road, 3 joint mechanisms to facilitate the connection of tertiary nodes to TEN-T infrastructure
Programme results: 13,546 people served by modernized infrastructure leading to TEN-T
Project status
The project is in the implementation period and the following results were achieved:
Lead Beneficiary:
LB started the execution of the construction works, but on 17.12.2020 the execution was suspended to solve some technical problems. The construction works were resumed on 23.08.2021, the duration of the construction works contract being 12 months and suspended, again, in December 2021 for the winter season, and the works were resumed on 15.03.2022.
Currently, the execution of the works has been suspended during the winter, starting with the dates of 16.12.2022, and they will resume in March 2023. The physical stage of the LB works is 41.12%.
Beneficiary 2:
The construction works for the B2's investment objective “Upgrading of Road II-81 from km 86+289 to km 94+000 ”, have been completed. On the upgraded road sector, being part of B2 investment, were installed 4 solar radar speed signs. The road use authorization was issued on 01.02.2022.