NAVY–T WAY (ROBG–478)
Improving safety of navigability on Danube River in the Calarasi – Silistra cross – border region
What’s the goal?
To improve the infrastructure on the both sides of the Danube river in order to maintain the navigability on the Danube.
What’s the budget?
5,946,041.76 euro, out of which 5.054.135.48 euro ERDF
Who is doing it?
Lead Beneficiary (LB): Territorial Administrative Unit – Calarasi County
Beneficiary 2 (B2): Silistra Municipality
Beneficiary 3 (B3): Territorial Administrative Unit – Calarasi Town
When is it happening?
Start date: 30.03.2019
End date: 31.12.2023
Duration: 57 months and 2 days
Where is it happening?
Silistra in Bulgaria
Calarasi in Romania
How is it going to happen?
- Strategies and action plans to improve the safety of the navigation on the Danube;
- Works in Calarasi County – to facilitate the direct access of the boat owners from one community to another, offering an open area of navigation on the inside Borcea arm;
- Works in Silistra District – rehabilitation of Riverside fortification walls;
- Promotional activities focus on providing project information, transparency and effective communication with stakeholders, as well as presenting the results of project activities and target groups and local stakeholders working in the cross-border region;
- The transport waterway between Calarasi and Silistra will be improved by installing beacons on 5 km inland waterway on the Borcea – secondary arm of Danube. Two river station will be developed, one for each side of the Danube. Two river buses of medium size will be purchase for passengers transportation.
What will be the results (what’s the contribution to the Programme)?
Programme outputs: Total length of new and improved inland waterway – 11 km;
Programme results: 2.34 % of the RO-BG CBC Danube length and Black Sea where safety of the navigation have been improved.
Project status
The project is currently under implementation with the following results reported so far:
LB – The contract for the technical design was signed (investments for Borcea arm). The Start Order for elaboration of the Technical Project was issued in the middle of November 2020. The development of the Technical Project together with all obtained permits was completed in the end of March 2021. In addition, contract for the purchase of a Amphibia was signed and the respective equipment is in process of testing and official reception by the LB.
B2 – Based on the received permission for construction, B2 started the works execution in Port of Silistra in the end of May 2023. So far, the percentage of the physical works execution has reached 71%. Furthermore, B2 succeed to sign also a contract for delivery of a Katamaran for 28 passengers and currently the respective equipment is expected to be officially delivered to B2.
B3 - LB has started the procedures to clear the land of the investment, demolishing the existing constructions on site. A contract for execution of the construction works in Borcea arm was signed in November 2021 and the Start Order for works execution was issued in the middle of December 2021. So far, the works execution level as a percentage has reached approximate 62%.