The streamline of the traffic in the cross border Danubian area

What’s the goal?

To improve the planning, development and coordination of cross border transport systems for better connections to TEN-T transport network.

What’s the budget?

7,943,701.93 euro, out of which 6,752,146.63 ERDF

Who’s doing it?

Lead beneficiary (LB): Territorial Administrative Unit - Mehedinti County (Romania)

Beneficiary 2 (B2): Dolna Mitropolia Municipality (Bulgaria)

When is it happening?

Start date: 12.12.2017

End date: 11.12.2023

Duration: 72 months

Where is it happening?

Cerneti, Dedovita Noua, Dedovita Veche, Valea Copcii, Dudasu, Alunisu, Baditesti, Husnicioara, Borogea, Celnata, Dumbravita, Marmanu, Opranesti, Peri, Priboiesti, Selisteni, Prunisor, Balota, Cervenita, Lumnic, Zegaia, Paltinisu, Govodarva, Rosia, Negresti, Mehedinti County, Romania

Dolna Mitropolia, Podem, Riben, Bozhurets, Pobeda and Bivolare, Dolna Mitropolia Municipality,Pleven District, Bulgaria

How’s it going to happen?

  • 27,38 km modernized on the Romanian territory - modernization DJ607A – Ringroad Drobeta - TurnuSeverin–Cerneti – ValeaCopcii – Peri – Prunisor (E70-TEN-T);
  • 6,450 km modernized on the Bulgarian territory - rehabilitation of road PVN1041, road PVN2046 and road PVN3044;
  • Organizing 3 press conferences and 8 press releases (4 in Romania, 4 in Bulgaria);
  • Information and publicity materials (temporary and permanent billboards);

What will be the results (what’s the contribution to the Programme)?

Programme outputs:

- 33,83 km total length of reconstructed or upgraded roads

Programme results: Cross border population (535,142 people: Pleven District = 269,752 persons and Mehedinti County = 265,390 persons) served by modernized infrastructure leading to TEN-T

Project status:

Considering that the project envisages road rehabilitation, the main progress registered at project level consists of the actions implemented by both project partners so far, as detailed below:

LB Territorial Administrative Unit - Mehedinti County (Romania)has started the execution of the works for modernization of DJ607A – Ringroad Drobeta - TurnuSeverin–Cerneti – ValeaCopcii – Peri – Prunisor (E70-TEN-T in the middle of May 2020 and currently the construction works are ongoing). The physical stage of the works has reached 28% so far, representing the execution of tubular bridges, dalat bridges, docking boxes, cassette execution, execution of broken stone foundation at the abutments, execution of consolidated approach cassettes, ballast profiling and scarification, crushed stone bedding and binder layer bedding and side road arrangement. The construction works are expected to be finalized until October 2023.

B2 Municipality of Dolna Mitropolia succeeded to finalize the execution of the works for the investment objective 2 – „Rehabilitation of Municipal road network of PVN 2046 / ІІІ-118, Podem – Dolna Mitropolia / - Bivolare/ PVN 1042”,Km 0+00 – Km 1+800” and investment objective 3 -„Rehabilitation of Municipal road network of PVN 3044 / ІІІ-118, Podem – Dolna Mitropolia / - Bozhuritsa / PVN 1042, from Km 0+000 to Km 2+100”, since the beginning of June 2020. The construction works, which are part from investment objective 1 - „Rehabilitation of Municipal road network of PVN 1041/ ІІІ-118, Komarevo - Dolna Mitropolia / - Podem - Riben - DZS 1 MAY from Km 0 + 750 to Km 3 + 300“ were also finalized in the beginning of August 2020, therefore completeing the modernization of 6.45 km of road facilitating access to TEN-T network.

Financial progress:

According to the information from the e-MS, the financial progress for each partner is as it follows:

LB - declared amount: 583,969.84 euro for period 0-6. The amount represent 11.55% of the total partner budget (5,058,051.76 euro). The certified amount is 583,946.82 euro – 11.54% of the total budget.

B2 - declared amounts: 2,489,838.70 euro for periods 0 - 6. The amount represents 86.28 % from the total partner budget (2,885,650.17 euro). The certified amount is 2,279,501.23 euro – 78.99 % of the budget.

The financial progress of the project at this moment is 38.69 % (the total amount declared 3,073,808.54 euro) from the total budget of the project (7,943,701.93 euro);

Pictures

The content of this website does not necessarily represent the official position of the European Union. The initiators of the site are the sole responsible for the information provided through the site.