STD (ROBG-138)

The streamline of the traffic in the cross border Danubian area

What’s the goal?

To improve the planning, development and coordination of cross border transport systems for better connections to TEN-T transport network.

What’s the budget?

7,943,701.93 euro, out of which 6,752,146.63 ERDF

Who’s doing it?

Lead beneficiary (LB): Territorial Administrative Unit - Mehedinti County (Romania)

Beneficiary 2 (B2): Dolna Mitropolia Municipality (Bulgaria)

When is it happening?

Start date: 12.12.2017

End date: 11.07.2023

Duration: 67 months

Where is it happening?

Cerneti, Dedovita Noua, Dedovita Veche, Valea Copcii, Dudasu, Alunisu, Baditesti, Husnicioara, Borogea, Celnata, Dumbravita, Marmanu, Opranesti, Peri, Priboiesti, Selisteni, Prunisor, Balota, Cervenita, Lumnic, Zegaia, Paltinisu, Govodarva, Rosia, Negresti, Mehedinti County, Romania

Dolna Mitropolia, Podem, Riben, Bozhurets, Pobeda and Bivolare, Dolna Mitropolia Municipality,Pleven District, Bulgaria

How’s it going to happen?

  • 27,819 km modernized on the Romanian territory - modernization DJ607A – Ringroad Drobeta - TurnuSeverin–Cerneti – ValeaCopcii – Peri – Prunisor (E70-TEN-T);
  • 6,450 km modernized on the Bulgarian territory - rehabilitation of road PVN1041, road PVN2046 and road PVN3044;
  • Organizing 3 press conferences and 8 press releases (4 in Romania, 4 in Bulgaria);
  • Information and publicity materials (temporary and permanent billboards);

What will be the results (what’s the contribution to the Programme)?

Programme outputs:

- 34,269 km total length of reconstructed or upgraded roads

Programme results: Cross border population (535,142 people: Pleven District = 269,752 persons and Mehedinti County = 265,390 persons) served by modernized infrastructure leading to TEN-T

Project status:

Considering that the project envisages road rehabilitation, the main progress registered at project level consists of the actions implemented by both project partners so far, as detailed below:

Lead Beneficiary - LB has updated the feasibility study and launched for the third time the public procurement procedure for design and works for modernization of 27.819 km of roads (DJ607A – Ringroad Drobeta – TurnuSeverin–Cerneti – ValeaCopcii – Peri – Prunisor -E70-TEN-T), in September 2019. Following the evaluation process of the three offers received, an execution contract was signed in January 2020.

Beneficiary 2 succeeded to assess the submitted offers and awarded three distinct contracts (for each of the three sections - road PVN1041, road PVN2046 and road PVN3044, a different contract was signed for the elaboration of the technical design and works execution). Following the signed contracts, the construction sites of all three Lots of the investment were opened in the end of November 2019. The construction works are already ongoing, still in very early stage of execution.

                                                          